What installation accuracy requirements should be paid attention to when installing condensing steam turbines?


In the industrial field, as an important power equipment, the scientific and rigorous installation process of condensing steam turbines directly affects the normal operation and performance of the equipment. 1、 The basic preparation for the installation process first requires an evaluation and preparation of the installation site to ensure a solid and level foundation. According to the design requirements of the steam turbine, make a sturdy concrete foundation and reserve installation connection parts such as anchor bolt holes. Measure the levelness and elevation of the foundation to ensure that its flatness is within the specified error range. Generally speaking, the basic levelness error should be controlled within 0.1 millimeters per meter

In the industrial field, as an important power equipment, the scientific and rigorous installation process of condensing steam turbines directly affects the normal operation and performance of the equipment.

1、 Installation process

Basic preparation

Firstly, the installation site needs to be evaluated and prepared to ensure a solid and level foundation. According to the design requirements of the steam turbine, make a sturdy concrete foundation and reserve installation connection parts such as anchor bolt holes.

Measure the levelness and elevation of the foundation to ensure that its flatness is within the specified error range. Generally speaking, the levelness error of the foundation should be controlled within 0.1 millimeters per meter, and the elevation error should be controlled within ± 5 millimeters.

淄博荏奥汽轮机有限公司

Equipment acceptance and handling

Conduct strict acceptance checks on the equipment. Check if all components of the steam turbine are complete and undamaged, and verify if the equipment model, specifications, and technical parameters match the design requirements.

Use appropriate handling tools and methods to safely transport the various components of the steam turbine to the installation position. During the transportation process, special attention should be paid to protecting key parts of the equipment, such as rotors, blades, etc., to prevent collisions and damage.

  汽缸安装

  将汽缸下半部分放置在基础上,通过调整垫铁等方式,使汽缸的中心线与基础的中心线重合。然后,使用水平仪对汽缸的水平度进行测量和调整,确保汽缸的水平度误差在每米不超过 0.05 毫米。

  安装汽缸的定位销和连接螺栓,按照规定的扭矩值进行紧固。在紧固螺栓时,要采用对角拧紧的方法,确保汽缸的安装牢固且均匀受力。

  转子安装

  对转子进行清洗和检查,确保转子表面光滑、无损伤。然后,将转子缓慢地吊入汽缸内,注意保持转子的水平和垂直状态。

  在转子安装到位后,进行轴瓦的安装和调整。轴瓦的间隙要根据设备的技术要求进行精确调整,一般来说,轴瓦的顶间隙应为轴颈直径的 0.15%~0.2%,侧间隙应为顶间隙的一半。

  叶片安装

  叶片是汽轮机的关键部件之一,其安装质量直接影响汽轮机的性能。在安装叶片时,要按照设计要求进行正确的装配顺序和方法。

  确保叶片的安装角度和间隙符合技术标准。叶片的安装角度误差应控制在±0.5°以内,叶片之间的间隙误差应控制在±0.1 毫米以内。

  凝汽器安装

  凝汽器的安装位置要靠近汽轮机,以便于蒸汽管道的连接。将凝汽器放置在基础上,调整其水平度和标高,使其与汽轮机接口对齐。

  安装凝汽器的冷却水管和抽气管道,确保管道连接牢固、密封良好。在安装过程中,要注意防止管道内部进入杂物,影响冷却效果。

  管道连接

  按照设计图纸,将汽轮机与蒸汽源、凝汽器、润滑油系统等进行管道连接。在连接过程中,要确保管道的走向合理、坡度适当,避免出现管道弯曲过度或积水等问题。

  对管道的连接部位进行焊接或法兰连接,焊接质量要符合相关标准,法兰连接的密封垫要选择合适的材质和规格,确保密封可靠。

  调试与试运行

  在完成设备安装后,进行全面的调试工作。包括电气系统调试、润滑系统调试、调速系统调试等。

  进行汽轮机的空载试运行和带负荷试运行,在试运行过程中,要密切观察设备的运行状态,检查各部位的温度、压力、振动等参数是否正常。对发现的问题及时进行调整和修复。

  二、安装精度要求注意事项

  中心线对中精度

  汽轮机的各个部件在安装时,必须保证其中心线在同一条直线上。尤其是汽轮机与发电机之间的连接,中心线的偏差应控制在 0.05 毫米以内。否则,会导致设备运行时振动增大、轴承磨损加剧等问题。

  水平度精度

  如前所述,汽缸、转子等关键部件的水平度要求非常严格。在安装过程中,要使用高精度的水平仪进行多次测量和调整,确保水平度误差在规定范围内。任何微小的水平度偏差都可能影响设备的运行稳定性和效率。

  间隙精度

  轴瓦与转子之间的间隙、叶片与汽缸之间的间隙等都需要精确控制。间隙过大,会导致泄漏增加,降低设备效率;间隙过小,容易引起摩擦和发热,甚至损坏设备。因此,在安装过程中,要使用专业的测量工具,如塞尺等,对间隙进行精确测量和调整。

  连接螺栓紧固精度

  汽轮机的各个部件之间通过大量的连接螺栓进行固定,螺栓的紧固扭矩必须按照设计要求进行严格控制。紧固不足,可能导致设备在运行过程中出现松动和泄漏;紧固过度,可能会损坏螺栓或部件。一般来说,螺栓的紧固扭矩误差应控制在±5%以内。

  密封精度

  汽轮机的密封性能直接影响其效率和安全性。汽缸的密封、管道的连接密封等都需要高度重视。在安装密封件时,要确保密封件的质量可靠,安装位置正确,压缩量符合要求。对于高温高压部位的密封,还要进行特殊的处理和检测,确保密封效果良好。

  总之,凝气式汽轮机的安装是一项复杂而精细的工作,需要严格按照安装流程和精度要求进行操作。只有这样,才能确保设备的安装质量,为其后续的正常运行和高效性能发挥奠定坚实的基础。在安装过程中,还需要专业的技术人员进行指导和监督,使用先进的测量和调试设备,确保每一个环节都符合标准和要求。